πŸ—οΈ GC Margin prototype
DEMO DATA

Demo mode β€” changes won’t be saved. Try the tools with sample data. Reload to reset. Don’t enter real customer or financial information.

Job P&L by phase

Oak Harbor Whole-Home Reno Β· The Prewitt Family Trust Β· contract $395,000.00
Change orders β†—Schedule β†—Subcontractors β†—Billing β†—
PhaseBudget (edit)CommittedActual CTDCTC (est / override)Projected margin%
Demo & Site Prep
$4,294.00$21,419.00
($22,644.11)-90%
Rough Framing
$14,060.00$52,531.48
($23,431.94)-25%
MEP Rough
$8,205.00$16,250.00
$7,285.3913%
Drywall & Paint
$10,685.00$4,170.00
$44,207.7862%
Finishes
$14,500.00$0.00
$53,055.7867%
Total$323,930.00$51,744.00$94,370.48$119,342.63$58,472.8918%

Committed = legacy sub commitments + open (unreceived) purchase-order balances. Actual reads the job_cost_entries ledger.

Cost breakdown by category (from the ledger)

PhaseLabor β€” baseLabor β€” burdenMaterialsEquipmentSubcontractOther/overheadTotal
Demo & Site Prep$0.00$0.00$2,320.00$429.00$6,753.97$11,916.03$21,419.00
Rough Framing$3,418.00$888.48$0.00$1,140.00$21,559.22$25,525.78$52,531.48
MEP Rough$0.00$0.00$0.00$0.00$7,653.29$8,596.71$16,250.00
Drywall & Paint$0.00$0.00$870.00$0.00$1,073.39$2,226.61$4,170.00
Finishes$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total$94,370.48

Labor burden shown separately β€” that's the number an owner argues about. Materials include PO receipts and inventory issues at moving-average cost.

Portfolio roll-up β€” Harbor Light Renovations

JobContractBudgetCommittedActual CTDCTCProj. margin%
Maple Street Kitchen & Bath$148,000.00$121,370.00$23,840.00$114,704.48$24,706.71($41,881.19)-35%
Oak Harbor Whole-Home Reno$395,000.00$323,930.00$51,744.00$94,370.48$119,342.63$58,472.8918%
Bayview Attic Conversion$82,000.00$67,250.00$4,485.00$11,468.94$67,250.00($15,953.94)-24%
Portfolio$625,000.00$512,550.00$80,069.00$220,543.90$211,299.33$637.770%